Construction schedule (Gantt, computed critical path)
A residential construction Gantt on a continuous calendar — excavation through handover. The engine computes the critical path (excavation → foundation → framing → electrical → drywall → finishes → handover) and shows the float on the parallel roofing and plumbing trades.
For the site planner sequencing trades
What this shows
Once framing finishes, three trades — roofing, electrical, plumbing — run in parallel, but drywall can't start until all three are done. The engine works out that electrical is the longest of the three, so it lands on the critical path while roofing and plumbing carry float (drawn in blue with their slack). The critical chain Excavation → Foundation → Framing → Electrical → Drywall → Finishes → Handover is in red, and Handover is a milestone diamond. On a continuous calendar the bars span weekends; switch to calendar: 5day for a working-day timeline.